STANDARD RFP TERMS - Ridgeline DC2 (owner-furnished equipment) Project: Ridgeline DC2, Building 2 Procurement contact: Jordan Price, Equipment Procurement RFPs go out: Friday 13 November 2026 Responses due: Tuesday 15 December 2026, 5:00 p.m. Eastern Payment: Milestones set in the purchase order; Net 30 from each approved invoice Warranty: 12 months from startup or 18 months from shipment, whichever comes first Delivery: Inside delivery to final position, rigging included. Coordinate crane, rigging and staging with the general contractor. Submittals: Shop drawings within 4 weeks of PO. O&M manuals at delivery. Factory test reports before shipment. Change orders: Written approval required for any change to scope, cost or schedule. Evaluation: Technical compliance 30%, price 30%, delivery schedule 20%, vendor experience 10%, warranty and support 10% Liquidated damages: amount set for each contract - not decided yet Insurance: amounts set for each contract - not decided yet